The PM-MITRA scheme is focused on which of the following objectives?

  1. AExpanding petroleum retail chains
  2. BDeveloping large integrated textile and apparel parksCorrect answer
  3. CCreating rail-based infrastructure hubs
  4. DProviding smart classrooms in rural schools
Show AnswerHide Answer

Answer

B. Developing large integrated textile and apparel parks

Show ExplanationHide Explanation

Explanation

PM MITRA supports large integrated textile parks. The parks are intended to bring multiple stages of textile production together and strengthen competitiveness.